The School is already in the process of getting affiliation to the Central Board of Secondary Education (CBSE). The Sera Mey Monastery’s Abbot along with 3 of the School staff was to the Office of the District Commissioner (DC) for their approval and granting of the No Objection Certificate (NOC) for the onward submission of the application to the CBSE Board in New Delhi.  It is a long process but the School is given the hope that the affiliation will come to be granted by the Board in Delhi although it may take some time.

At the same time, the School is working hard to have the entire infrastructure, systems and other necessary requirements in place to upgrade the School from a Primary School to a Secondary School.  The School will surely be very ready to start class IX (in the first year and also then class X in the second year) as soon as the affiliation is granted.

Meeting with Prof. Gopal Krishna Joshi, Director, Karnataka State Higher Education Council.
Mr Shivamurthy & Mr Suresh from the Office of the DDPI, Mysore
Mrs Harpreet Kaur interacting with the children during the Morning Assembly
Mrs Kaur's Interaction and Q&A session with the teachers
Meeting with the Abbot of Sera Mey Monastery

Update Update

Staff Quarter Construction

Sermey Thoesam School is facing a big shortage of Staff Quarters as now most of the new teacher applicants are coming from outside of the Bylakuppe Settlement.  At the same time, the existing Staff Quarter was not built (built in the 1980s) as a proper Staff Quarter so it is lacking in quite a many aspects.  There is shortage of toilet, bath and proper kitchen in the Quarters.

The School Management is hoping to do at least 21 sets of Quarters on the available land belonging to the Sera Mey Monastery. The rough estimation is that it will cost around 447L rupees (approx. half million US dollars). The process will begin in the near future as accommodation shortage needs to be addressed sooner rather than later.

We are sharing few site photos of the on going work for your kind information (Nov 06 2024)

Project TimeLine

The construction work (Foundation) started on 26th December, 2022 with the Groundbreaking ceremony held on the site
3 months later, the Foundation is complete
From 31.3.2023 the work on the "1st Floor" quarters will begin
Complete Ground Floor Construction.
First Floor Work going
Staff Quarter 2nd Floor Construction Beginning. The project is going on per schedule.
Dec 26th, 2022
Mar, 2023
Mar 31, 2023
June 1st, 2023
August, 2023
As of Now